Is the flexibilisation of formal requirements in public procurement going both ways? (T-394/12)

In its Judgment in Alfastar Benelux v Council, T-394/12, EU:T:2014:992, the General Court (GC) resolved a dispute concerning public procurement activity of the European Institutions (in this case, the Council). One of the main claims of the disappointed bidder was that the Council had failed to discharge its obligation to state reasons because one of the sentences of the extracted evaluation report that was made available to it by the Council was incomplete.
 
In the applicant's view, the incompleteness of the extract prevented it from assessing the reasons that justified the Council's decision to award the contract to another tenderer. The applicant submitted that the fact that the Council had complemented the extract at a later stage did not overcome the initial ommission and that the Council should be made liable for damages. The GC rejected the claim. The reasoning of the GC in dismissing the action triggers some comments.
 
Firstly, it is worth emphasising that the GC has continued pushing for a strengthening of the duty to provide reasons in abstracto (and, indirectly, as a result of the bindingness of the right to good administration as recognised in Art 41(2)(c) of the EU Charter of Fundamental Rights). Indeed, the GC emphasised that, as a general point of law,
since infringement of the obligation to give reasons is a matter of public interest, the European Union judicature must raise it of its own motion and, therefore, the fact that the applicant raised it belatedly does not render such a plea inadmissible (see, to that effect, BP Products North America v Council, T-385/11, EU:T:2014:7, paragraph 164) (T-394/12 at para 25, emphasis added).
This creates a strong incentive for contracting authorities to 'err on the side of excessive disclosure' when it comes to the reasons for the adoption of a procurement decision, which may be detrimental for competition and for the protection of the legitimate commercial interests of other tenderers (as clearly recognised in art 55(3) Dir 2014/24 and art 113(2)II Financial Reg, but not always properly understood or applied). This also follows on the GC's previous tough approach and continues to create excessive incentives towards transparency in public procurement (as criticised here, here and in A Sánchez Graells, 'The Difficult Balance between Transparency and Competition in Public Procurement: Some Recent Trends in the Case Law of the European Courts and a Look at the New Directives', University of Leicester School of Law Research Paper No. 13-11). Hence, the general approach continues to create the wrong incentives and should be reassessed.
 
Secondly, however, when it comes to the specifics of the case, the GC adopts a very sensible and reasonable approach to the assessment of the claim of breach of the duty to state reasons in particular. Indeed, the GC dismisses the claim on the basis that the incomplete sentence only omitted a limited amount of information concerning the general comments of the evaluators and, additionally, the tenderer had been provided with more details in the remainder of the extract from the evaluation report. Interestingly, the GC stressed that
The general comments may easily be inferred from the detailed technical evaluations of the successful tenderer’s bid which are not concerned by the formatting error, since the general comments constitute a succinct summary of material contained in the contested decision (T-394/12 at para 30, emphasis added).
As such, this reasoning should not be surprising and the GC could hardly be expected to have decided otherwise. Having adopted a more formalistic approach would not only have annulled a procurement decision for no good reason, but would also have opened the floodgates to an unforeseeable volume of litigation (particularly if one takes into account that the guarantees provided by Art 41 EUCFR are applicable in all procurement covered by Dir 2014/24). Hence, it is a sensible decision.
 
However, the better question seems to be whether this same 'anti-formalistic' approach will hold when the clerical mistakes and partial ommissions affect the documentation submitted by the tenderers. Functionally, the rules applicable to the interpretation of documents and the avoidance of formal requirements where the parties engaged in the procurement process 'can make sense' of the documentation exchanged should go both ways. However, this is not necessarily the case yet, as recently discussed regarding Cartiera dell’Adda and Cartiera di Cologno, C-42/13, EU:C:2014:2345 (see here).
 
Hence, it will be interesting to see if the incipient push towards a more functional approach to public procurement takes root and ends up creating a system that is less 'based on rights' and more oriented towards good procurement outcomes [a problem that also affects 'the other side of the Atlantic', as discussed in S Schooner & P Kovacs, "Affirmatively Inefficient Jurisprudence?: Confusing Contractors’ Rights to Raise Affirmative Defenses with Sovereign Immunity" (2012) 21 Federal Circuit Bar Journal 686].

It's for the GC to decide, but it's not ok: CJEU rules on 'excessive duration' of competition law litigation (C-40/12 P)


In a batch of impatiently expected Judgments of 26 November 2012, the CJEU has ruled on the procedural and substantial rules applicable to a claim that (competition law) litigation before the General Court was of an 'excessive duration' and, consequently, breached Article 47 of the Charter of Fundamental Rights of the EU. In my view, this is another instance of a rather convoluted legal construction by the CJEU whereby it rejects its jurisdiction (on formal points), but actually addresses the substantial points in a way that leaves no room whatsoever for the GC when the matter is presented before it for a fresh consideraton--and, consequently, raises the question whether the system is sensibly designed to begin with...
 
In its Judgment in case C-40/12 P Gascogne Sack Deutschland (anciennement Sachsa Verpackung) v Commission, the CJEU has clearly indicated that
89 [...] the sanction for a breach, by a Court of the European Union, of its obligation under the second paragraph of Article 47 of the Charter to adjudicate on the cases before it within a reasonable time must be an action for damages brought before the General Court, since such an action constitutes an effective remedy.

90 It follows that a claim for compensation for the damage caused by the failure by the General Court to adjudicate within a reasonable time may not be made directly to the Court of Justice in the context of an appeal, but must be brought before the General Court itself.

91 As regards the criteria for assessing whether the General Court has observed the reasonable time principle, it must be borne in mind that the reasonableness of the period for delivering judgment is to be appraised in the light of the circumstances specific to each case, such as the complexity of the case and the conduct of the parties (see, in particular, Der Grüne Punkt – Duales System Deutschland v Commission, paragraph 181 and the case-law cited).

92 The Court has held in that regard that the list of relevant criteria is not exhaustive and that the assessment of the reasonableness of a period does not require a systematic examination of the circumstances of the case in the light of each of them, where the duration of the proceedings appears justified in the light of one of them. Thus, the complexity of the case or the dilatory conduct of the applicant may be deemed to justify a duration which is prima facie too long (see, in particular, Der Grüne Punkt – Duales System Deutschland v Commission, paragraph 182 and the case-law cited).

93 In examining those criteria, it must be borne in mind that, in the case of proceedings concerning infringement of competition rules, the fundamental requirement of legal certainty on which economic operators must be able to rely and the aim of ensuring that competition is not distorted in the internal market are of considerable importance not only for an applicant itself and its competitors but also for third parties, in view of the large number of persons concerned and the financial interests involved (see, in particular, Der Grüne Punkt – Duales System Deutschland v Commission, paragraph 186 and the case-law cited).

94 It will also be for the General Court to assess both the actual existence of the harm alleged and the causal connection between that harm and the excessive length of the legal proceedings in dispute by examining the evidence submitted for that purpose.

95 In that regard, it should be noted that, in an action for damages based on a breach by the General Court of the second paragraph of Article 47 of the Charter, in so far as it failed to have regard to the requirement that the case be dealt with within a reasonable time, the General Court must, in accordance with the second paragraph of Article 340 TFEU, take into consideration the general principles applicable in the legal systems of the Member States for actions based on similar breaches. In that context, the General Court must, in particular, ascertain whether it is possible to identify, in addition to any material loss, any other type of harm sustained by the party affected by the excessive period, which should, where appropriate, be suitably compensated.

96 It is therefore for the General Court, which has jurisdiction under Article 256(1) TFEU, to determine such claims for damages, sitting in a different composition from that which heard the dispute giving rise to the procedure whose duration is criticised and applying the criteria set out in paragraphs 91 to 95 above
(C-40/12 P at paras 89-96, emphasis added).
So far, the general framework depicted by the CJEU makes sense and, even if it creates a potential problem of conflict of interest derived from the 'self-assessment' required from the GC (despite its seating in a different composition), the remedy is clearly outlined and the material or substantive conditions that should be taken into account are also spelled out in a relatively easy to apply test (although some deference towards lengthy competition litigation seems to be readable between the lines).
 
However, the temptation ends up being too strong and the CJEU, maybe aware of the intractability of that conflict of interest, cannot refrain itself from actually settling the matter (despite concluding it has to reject the ground for appeal!). Hence, the CJEU carries on to make clear that

97 That said, it must be stated that the length of the proceedings before the General Court, which amounted to approximately 5 years and 9 months, cannot be justified by any of the particular circumstances of the present case.

98 It is apparent, in particular, that the period between the end of the written procedure, when the Commission’s rejoinder was lodged in February 2007, and the opening, in December 2010, of the oral procedure lasted for approximately 3 years and 10 months. The length of that period cannot be explained by the circumstances of the case, whether it be the complexity of the dispute, the conduct of the parties or supervening procedural matters.

99 As regards the complexity of the dispute, it is apparent from examining the action brought by the appellant, as summarised in paragraphs 12 and 13 above, that, while requiring a detailed examination, the pleas relied on did not present any particular difficulties. Although it is true that around 15 addressees of the contested decision brought actions for its annulment before the General Court, that fact could not prevent it from scrutinising the documents in the case and preparing for the oral procedure within a period of less than 3 years and 10 months.

100 It must be pointed out that, during that period, the procedure was not interrupted or delayed by the adoption of any measures of organisation of procedure by the General Court.

101 As regards the conduct of the parties and supervening procedural matters, the fact that the appellant requested, in October 2010, the reopening of the written procedure cannot justify the period of 3 years and 8 months which had already elapsed since it was closed. In addition, as the Advocate General observed in point 134 of her Opinion, the fact that the appellant was notified in December 2010 that there would be a hearing in February 2011 shows that that procedural matter had only a minimal effect on the overall length of proceedings, or even no effect at all.

102 In the light of the foregoing, it must be found that the procedure in the General Court breached the second paragraph of Article 47 of the Charter in that it failed to comply with the requirement that it adjudicate within a reasonable time, which constitutes a sufficiently serious breach of a rule of law that is intended to confer rights on individuals (Case C-352/98 P Bergaderm and Goupil v Commission [2000] ECR I-5291, paragraph 42).

103 It is, however, clear from the considerations set out at paragraphs 81 to 90 above that the fourth ground of appeal must be rejected
(sic) (C-40/12 P at paras 97-103, emphasis added). 
In my view, even if there is no question that the formal treatment of the claim for damages (ie the ground for appeal) is correct, the fact that the CJEU felt the urge to settle the matter from a substantive perspective shows that the attribution of the competence to hear cases concerned with the excessive duration of litigation before the GC to the GC itself (albeit in a different seating) makes poor sense and is likely to result in almost 100% of cases in a further appeal before the CJEU.
 
To be fair, if the CJEU assumed the competence from the beginning, other problems derived from a single-step or one-shot system where the claims would be shielded from potential appeals would also arise. So, it looks like we may be facing one of those areas where a clear limitation of the institutional design of the EU Courts seems apparent and where pressure for the future potential referral of the cases to the Strasbourg Court may be felt.
 
However, as indicated yesterday when commenting a timely editorial opinion of Advocate General Sharpston (here), it may well be that the granting of excessive procedural rights to competition law defendants end up in an unmanageable workload for the EU Courts (as well as for the European Court of Human Rights) and, consequently, a deeper revision of the system seems necessary [see my further developed aruments in The EU’s Accession to the ECHR and Due Process Rights in EU Competition Law Matters: Nothing New Under the Sun?].

"You have been warned": AG Sharpston's concerns should be sorted out differently


In an interesting and provocative editorial comment entitled 'Effective Judicial Protection through Adequate Judicial Scrutiny—Some Reflections' [Journal of European Competition Law & Practice (2013) 4(6): 453-454], Advocate General Eleanor Sharpston comments on the difficulties that the Court of Justice of the EU faces in its endeavor to uphold the right to effective judicial protection enshrined both in the European Convention of Human Rights (art 13) and in the Charter of Fundamental Rights of the European Union (art 47)--which, in competition law enforcement, also involves some due process guarantees of Article 6 ECHR.
 
Basically, AG Sharpston is concerned with whatever can be done to ensure that effective judicial review of competition law sanctions does not produce unreasonable delay and thus defeats the purpose of the exercise.
 
By reference to recent cases in which the review conducted by the General Court has been challenged on the basis of the fundamental right to obtain judicial review within a reasonable time, AG Sharpston offers a rather detailed account of the practical difficulties and burdens derived from the way the EU Courts work and explores potential avenues of (institutional) reform that could alleviate those constraints. Maybe not surprinsingly, after considering that incremental change (or change by means of internal reform) has clear limits, AG Sharpston suggests that the EU Courts (particularly the General Court) should grow in terms of available judicial manpower and that the members of the EU Courts should be given more continuity and stability in their appointments. A political economy analysis of these proposals may be interesting (is it not in the essence of any institution to aim to grow and perpetuate itself?), but is not what I consider more interesting after reading the editorial. I think that there are two elements in AG Sharpston's reflections that deserve some emphasis.
 
On the one hand, I think that this is a case that shows the need for some clear boundaries in what active members of the judiciary in its highest ranks, such as an Advocate General, may say and publish. There is a clear need for them to thread lightly and think carefully about the (personal) opinions that they decide to make public. I say this because, in a very provocative passage, AG Sharpston advances a 'creative' solution to the problem of the excessive workload of the EU Courts in the following terms:
the advocate pleading competition cases before the EU courts, or the in-house adviser analysing the merits of challenging a Commission decision or lodging an appeal—can also make a major contribution towards ensuring that the courts function effectively and smoothly and can deliver effective judicial review. Please (I beg you) consolidate your arguments and only run with the points that have some real substance to them. Don't put in an application with six grounds of appeal, each divided into several sub-points (you know, and I know, that not all are of equal merit!). Please plead succinctly and clearly (think of translation!) and please don't throw in an additional 600 pages of annexes in case something there might help to swing the case your way. And, by the way: please don't appeal a clearly hopeless case to the Court of Justice just to show the client that you've tried everything you can. We too are worried about our workload—particularly the part of that workload that consists of wholly unmeritorious or manifestly inadmissible appeals—and we are looking at ways to streamline how we deal with such cases. You have been warned.
This half friendly, half jokingly-made warning may not be totally void of an underlying truth (in some cases at least), but many (myself for one) may see it as rather confrontational and such undercover criticisms of the bar may not sit well with non-UK practitioners. Moreover, it may put the Advocate General in a difficult situation when she has to intervene in cases where she may want to consider the claims unmeritorius (surely, if everybody is warned, she may feel more at ease to hand down rather blunt opinions, won't she?).
 
But, more importantly, I think that AG Sharpston is caught in the 'thinking inside the box' approach that she somehow criticises when she dismisses the potential for incremental change (or change by means of internal reform) to contribute to alleviate the current (permanent?) excessive workload of the EU Courts. Most of her views, and those expressed more generally by the CJEU when it comes to the interpretation and application of Articles 6 & 13 ECHR or 47 CFREU derive from the premise that
'[These rights are] increasingly frequently invoked by individuals claiming individual rights under EU law. [They are], however, no less a right for ‘undertakings’ (ordinary businesses) who fall foul of the competition rules and who find themselves on the receiving end of adverse decisions' (emphasis added).
I beg to fundamentally disagree with AG Sharpston on this crucial point. As I submitted in The EU’s Accession to the ECHR and Due Process Rights in EU Competition Law Matters: Nothing New Under the Sun?, undertakings (or companies) deserve a relatively more limited protection than individuals under the ECHR and, more specifically, under Article 6(1) ECHR—at least as regards non-core due process guarantees, such as the standard of review applicable to the revision of competition law decisions. In my opinion, only by acknowledging this and redimensioning the procedural guarantees granted to undertakings can the system be made manageable and the workload of the EU Courts rationalised and focused in areas of EU Law that require more effort and investment in terms of (human capital, judicial) resources. By following in the path dependence of granting undertakings full protection (ie implicitly, by making them beneficiaries of 'corporate human rights'), the problems can only become more and more intractable.
 
This is an issue on which I am conducting further research (which I hope to be able to publish soon) but, for the time being, suffice it to say that I consider AG Sharpston's editorial comment a clear indication of the fact that the CJEU does not seem to be aware that it is putting a nose around its neck by part-taking in the inflation of 'corporate human rights'--just as it is doing by favouring the hypertrophy of the preliminary reference mechanism, as already criticised here. If it wants to be part of the solution, maybe it could well start by minimising the problem.