ECJ extends justiciability of procurement infringements: No need to review the Remedies Directive? (C-391/15)

In its Judgment of 5 April 2017 in Marina del Mediterráneo and Others, C-391/15, EU:C:2017:268, the European Court of Justice (ECJ) issued another preliminary ruling on the scope of the Remedies Directive. The case required clarification on the concrete type of decisions that interested tenderers can challenge under the Remedies Directive.

In particular, the case sought clarification on whether the review procedures mandated by Art 2(1), and applicable to "decisions taken by the contracting authorities" (as per Art 1(1) Remedies Directive), had to allow a tenderer to challenge a decision by which the contracting authority allowed another economic operator to submit a tender in a public procurement procedure. That is, whether the Remedies Directive created standing to challenge exclusion and selection decisions that concerned other tenderers.

This issue can be seen as controversial because there are two ways in which the analysis can be framed. Firstly, it can be considered that a decision not to exclude (or to select) a competing tenderer does not necessarily produce adverse legal effects for other tenderers--and, consequently, there are no subjective rights to be protected at this stage. Secondly, and to the contrary, it can be considered that a decision that determines the number of competing tenderers among which the contracting authority needs to choose the awardee of the contract produces legal effects on all tenderers involved--and, consequently, there can be (soft?) subjective rights meriting protection both in decisions to exclude (vis-a-vis the excluded tenderer) and not to exclude (vis-a-vis all other tenderers).

The first approach to this issue would be closer to a strict interpretation of the procedural rights implicit in the participation in a procurement process--ie that unless a decision makes it impossible for a tenderer to continue its participation in the tender, there is no decision for which revision it has a legitimate interest / legal standing. The second approach is probably closer to a substantive interpretation of those same procedural rights, as well as supportive of a system of private oversight of compliance with (EU) public procurement law through private actions, where challenges on the basis of the illegality of exclusion and selection decisions are easier to accommodate.

In Marina del Mediterráneo, the relevant Spanish rules followed the first approach, and determined that: "the following acts may be the subject of the application [for judicial review]: (a) Contract notices, specifications and contractual documents laying down the conditions which will govern the procurement procedure; (b) Preparatory acts adopted in the tendering procedure, provided that they decide, directly or indirectly, the award of the contract, make it impossible to continue the procedure or to put up a defence, or cause irreparable harm to legitimate rights or interests. Acts of the procurement board which decide to exclude tenderers will be considered preparatory acts which make it impossible to continue the procedure; (c) Award decisions adopted by the contracting authorities" (C-391/15, para 11, emphasis added).

Thus, under Spanish law, a decision to exclude a tenderer can be challenged 'there and then' by the excluded tenderer, but a decision not to exclude (or to select) that tenderer can only be challenged by other tenderers at the end of the procedure (ie during standstill) and only on the basis of the illegality of the decision to award the contract to that particular tenderer and/or any of the preparatory acts for that decision. 

Therefore, by challenging the Spanish rule, the preliminary reference fundamentally--but rather implicitly--concerned the extent to which Arts 1(1) and 2(1) of the Remedies Directive can be transposed/interpreted in a way that limits the procurement decisions open to (separate, immediate) review to those that negatively affect the subjective rights of a tenderer (in a narrow construction), or whether those provisions create a catch-all category that makes (virtually) all decisions taken by the contracting authority along the procurement processes susceptible of (separate and particularised) review.

That not absolutely all decisions need to be subjected to the review procedures of the Remedies Directive was suggested on the basis of Commission v Spain (C‑214/00, EU:C:2003:276, para 80), where the Commission challenged the same Spanish rule for failing to ‘allow review to be sought of all decisions adopted by the contracting authorities, including all procedural measures, during the procedure for the award of public contracts’, and the ECJ rejected that maximalist approach on the basis that ‘the Commission has not established that that legislation does not provide adequate judicial protection for individuals harmed by infringements of the relevant rules of [Union] law or of the national rules transposing that law’. This could be seen as a decision purely on the (lack of) evidence adduced by the Commission. However, even if a wider reading of the ECJ decision is adopted to the effect that there may be procurement decisions that do not harm individual rights in a manner that merits (separate, immediate) review, the boundaries of the categories of decisions covered by the Remedies Directive remained all but fuzzy, and the extent to which Arts 1(1) and 2(1) of the Remedies Directive had to be interpreted in a restrictive or an expansive way required clarification.

It is worth stressing that AG Bobek (Opinion of 8 September 2016, C-391/15, EU:C:2016:651) was convinced by the first approach outlined above (ie a restrictive interpretation of the Remedies Directive) because constructing the remedies system "in such a broad and rather limitless way would mean that every single decision, however marginal and ancillary, could be immediately attacked, and the award procedure effectively halted. Yet, ... a reasonable balance must be struck between the different interests at stake in public procurement procedures, namely, the right of access to court and judicial review to challenge aspects of the procedure, on the one hand, and effectiveness of the overall procedure and judicial expediency, on the other" (para 34, footnote ommitted). 

Therefore, in an Opinion that seemingly tried to avoid declaring the necessary justiciability of (every) exclusion and selection decision, invited the ECJ to declare that national procedural rules could avoid subjecting those decision to direct (and specific) review provided that: "(a) the national legislation does not hinder immediate review of preparatory acts that produce adverse legal effects on undertakings; and (b) a plea of illegality of preparatory acts that do not produce adverse legal effects on undertakings, such as a decision to admit a candidate to a tendering procedure, can be made in support of an action against the final decision awarding the contract taken on the basis of those preparatory acts" (para 67) . 

In short, the ECJ disagreed with AG Bobek and found that, where there are allegations that a decision allowing a tenderer to participate in a procurement procedure was adopted in breach of EU public procurement law or the national legislation transposing it, national rules must class such decision among the preparatory acts of a contracting authority which may be subject to an independent judicial review--or, in simpler terms, that exclusion and selection decisions concerning other tenderers are open to the review procedures of the Remedies Directive. the reasons given by the ECJ are primarily that:

[the] broad construction of the concept of a ‘decision’ taken by a contracting authority is confirmed by the fact that Article 1(1) of [the Remedies Directive] does not lay down any restriction with regard to the nature or content of the decisions it refers to. Moreover, a restrictive interpretation of that concept would be incompatible with the terms of Article 2(1)(a) of that directive which requires Member States to make provision for interim relief procedures in relation to any decision taken by the contracting authorities (para 27).

And that:

... although [the Remedies Directive] has not formally laid down the time from which the possibility of review, as provided for in Article 1(1), must be open, the objective of that directive, as referred to in the preceding paragraph, does not authorise Member States to make the exercise of the right to apply for review conditional on the fact that the public procurement procedure in question has formally reached a particular stage ...  the fact that the national legislation at issue ... requires, in all cases, a tenderer to wait for a decision awarding the contract in question before it may apply for a review of a decision allowing another tenderer to participate in that procurement procedure infringes the provisions of [the Remedies Directive] (paras 31 and 34).

In my view, even if there are issues of consistency with previous case law that may require some additional fine tuning, there is no question that the ECJ has taken a very expansive approach to the interpretation of the Remedies Directive on this occasion, and that the thrust of the Marina del Mediterráneo Judgment reflects a wide approach to the provision of procurement remedies.

This puts significant pressure on domestic review procedures to ensure that virtually all decisions taken by a contracting authority can be challenged, and that the challenge is available as soon as possible -- and definitely before the award of the contract because as expressed in the "first and second recitals, [the Remedies Directive] is intended to strengthen the existing mechanisms, both at national and EU levels, to ensure the effective application of the directives relating to public procurement, in particular at a stage when infringements can still be corrected" (para 30). This is particularly relevant in view of the (unnecessary) declaration by the ECJ that "Articles 1(1) and 2(1)(a) and (b) of [the Remedies Directive have direct effect" (para 41), which will provide robust legal foundation to challenges against existing domestic rules on access to review procedures.

This approach is bound to further judicialise public procurement oversight through expanded justiciability of (exclusion, but not only) decisions, and puts renewed pressure on the development of more robust procurement review procedures by the Member States--possibly requiring a reform of the Remedies Directives themselves, as I discuss at length in "'If It Ain't Broke, Don't Fix It'? EU Requirements of Administrative Oversight and Judicial Protection for Public Contracts",  in S Torricelli & F Folliot Lalliot (eds), Administrative oversight and judicial protection for public contracts (forthcoming). In my view, this is not necessarily a blueprint for desirable regulatory reform and more thought needs to go into the balance between public compliance oversight and private enforcement of the EU public procurement rules. However, it seems out of the question that legal reform will be necessary (in Spain and elsewhere) and, in my view, that the European Commission abandoned the revision of the Remedies Directives too quickly.

#CJEU does not tolerate a slacker @EU_Commission in #Stateaid control (C-615/11): Commission counter-attacks with 'case management' excuses

In its Judgment of 16 May 2013 in case C-615/11 Commission v Ryanair, the Court of Justice of the European Union (CJEU) has dismissed the Commission's appeal against the prior Judgment of the General Court where it was found that the Commission failed to fulfill its obligations under the Treaty by not adopting a decision following a complaint lodged by Ryanair. 

Building up on the prior case law in Athinaïki Techniki AE v Commission (C-521/06), the CJEU has imposed upon the European Commission a clear duty to act when it is put in possession of information regarding alleged unlawful aid and called upon to to define its position within the meaning of Article 265(2) TFEU. In the view of the CJEU
27 As a preliminary point, it should be borne in mind that, under Article 20(2) of Regulation No 659/1999, any interested party may inform the Commission of any alleged unlawful aid and of any alleged misuse of aid.

28 Where it has in its possession information, from whatever source, regarding alleged unlawful aid, the Commission is required, under Article 10(1) of Regulation No 659/1999, immediately to examine the possible existence of aid and its compatibility with the internal market. The examination of such information, on the basis of that provision, gives rise to the initiation of the preliminary examination stage under Article 108(3) TFEU (see, to that effect, Case C‑322/09 P NDSHT v Commission [2010] ECR I‑11911, paragraph 49 and the case-law cited).

29 At that stage, and where it considers that there are insufficient grounds for taking a view on the case, the Commission, in accordance with the second sentence of Article 20(2) of Regulation No 659/1999, must communicate that finding to the interested parties which have sent it the information in question and must also allow those parties to submit additional comments within a reasonable period (see, to that effect, Athinaïki Techniki v Commission, paragraph 39).

30 Article 13(1) of Regulation No 659/1999, which is applicable in the context of an examination of alleged unlawful aid, obliges the Commission to close that preliminary examination stage by adopting a decision pursuant to Article 4(2), (3) or (4) of that regulation, that is to say, a decision finding that aid does not exist, raising no objections or initiating the formal investigation procedure, since that institution is not authorised to persist in its failure to act during the preliminary examination stage (Athinaïki Techniki v Commission, paragraph 40).

31 It follows […] that the preliminary examination stage, which ultimately obliges the Commission to take a position, requires that, where that examination is carried out on the initiative of an interested party, information concerning alleged unlawful aid be sent to the Commission by that party (C-615/11 at paras 27 to 31, emphasis added).
The extent of the Commission's duties is crystal clear and, consequently, the Institution should better internalize this obligation--which, more generally, is not much more than a specific expression of the duty of good administration that is increasingly recognised as a general principle of EU (Administrative) Law.

Indeed, this Judgment should seriously be taken into consideration in the current State Aid Modernisation (SAM) initiative--which the Commission should use to streamline its procedures as necessary to discharge the (raised) duty of diligence that derives from the CJEU's Ryanair Judgment. In this regard, it is positive to see that, as part of SAM (and probably in view of the defeat suffered before the GC and the likely, now actual, defeat before the CJEU), the Commission is already proposing to modernise the Procedural Regulation (659/1999) with regard to complaint-handling and market information tools. According to the Commission's proposal:
The Commission is required to conduct a diligent and impartial examination of complaints submitted from interested parties and take a decision thereon without undue delay. Where the Commission takes a decision finding that there exists no State aid as alleged by a complainant, the Commission must at least provide the complainant with an adequate explanation of the reasons for which the facts and points of law put forward in the complaint have failed to demonstrate the existence of State aid [COM(2012)0725 final, Explanatory Memorandum].

This begs the question why did the Commission not desist from the appeal in case C-615/11 if it had, itself, already assumed that it was in the wrong in the Ryanair case? (although the potential Art 340 TFEU claim for non-contractual liability of the European Commission that may follow today's CJEU Judgment seems the obvious explanation...).

Going back to the specific proposals of the Commission to improve the way it handles State aid complaints, the positive impression disappears when one realizes that the December 2012 proposal aims to modify Regulation 659/1999 to expressly regulate the way in which complaints need to be lodged--and, consequently, the reform is largely a 'self-defence' instrument for the European Commission, which feels overburdened by State aid complaints. As explained (excusation non petita...)
the Commission receives on average more than 300 complaints every year, whether lodged by interested parties or not, among which many are either not motivated by genuine competition concerns or not sufficiently substantiated. Most complaints are not treated as a priority and the average duration of those cases therefore tends to increase. Therefore, the complaints handling procedure is sometimes perceived by Member States and complainants as unpredictable and lacking transparency [COM(2012)0725 final, Explanatory Memorandum].
Hence, the Commission is proposing to consolidate in the regulation some of the 2009 Code of Best Practices for the conduct of State aid procedures, which expected benefits 'of shorter duration, increased efficiency and greater predictability – have not fully materialised [Moreover] Best Practices could not address some of the main shortcomings of the current system, since they directly stem from the Procedural Regulation. That is why a reform of the Procedural Regulation itself is proposed to address those issues.' Therefore, the European Commission proposed the following modifications:
In the interests of transparency and legal certainty (sic), the conditions to lodge a complaint which put the Commission in possession of information regarding alleged unlawful aid and thereby set in motion the preliminary examination should therefore be clarified. Indeed it is appropriate to require that:
complainants submit a certain amount of compulsory information. To that end, it is appropriate to empower the Commission to adopt implementing provisions to define the form and the content of a complaint.
complainants demonstrate that they are interested parties within the meaning of Article 108(2) TFEU and Article 1(h) of the Procedural Regulation and that they therefore have a legitimate interest to lodge a complaint. To reach that objective, it is proposed to specify in Article 20(2) on the "rights of interested parties" that "any interested party may lodge a complaint".
In cases where the information received will not be classified as a complaint since it will not have passed the admissibility criteria, the Commission will no longer be under an obligation to adopt formal decisions. Those submissions will be registered as market information and could be used at a later stage to conduct ex officio investigations.
To complete the staged procedure introduced by the Best Practices Code, the Procedural Regulation should formalise the possibility for the Commission to deem complaints withdrawn if the complainant does not return to it with meaningful information or otherwise fails to cooperate during the procedure. In that way, the treatment of complaints could be streamlined and improved (emphasis added and references omitted).
In my view, these changes are self-serving and would simply (aim to) deactivate the functional approach and the high duty of administrative diligence stressed by the CJEU in the Ryanair Judgment and, consequently, may diminish significantly the effectiveness of the complaints mechanism, sacrificing it in the altar of workload allocation and Commission liability-proofing. The trade-off may likely reduce the effectiveness of State aid control in the long run. 


Interestingly, these proposals were the object of a consultation and, hopefully, the Commission will issue a revised proposal in view of those and other considerations. In my opinion, given the very clear approach followed by the CJEU in Ryanair, the European Commission should abandon its self-centered approach to the reform of the rules on the handling of complaints in State aid cases and, in the spirit of institutional loyalty and in with the aim to keep (or develop) a well-functioning State aid control system, introduce more flexibility in the criteria for the lodging of complaints by (non)interested parties.